Review of Amended Site Plan Approval for 364 Main Street. Planner recused. Applicant's architect discussed architectural changes and field changes; constructed building has less square footage than approved. Board concerned about differences between approved and built design and impact on Main Street facade. Motion to circulate for lead agency approved.
Where this stands
Subdivision of land
We couldn't confidently place this on the process map from the public record. Here's the full path, and what we've seen so far.
- Sketch conference (optional)
- Preliminary plat submission
- Preliminary plat hearing
- Preliminary plat decision
- Final plat submission
- Final plat hearing (may be waived)
- Final plat decision
- Signing and recording
What we've seen
- First came before the boardOctober 12, 2022
- Review continuedJune 9, 2026
These plain-language summaries are unofficial guides to help residents follow the process. The linked provision text and the City of Beacon's official code are the authoritative sources.
See the full Subdivision of land guideAcross meetings
- October 12, 2022DiscussedSubdivision Approval
Extension request submitted before deadline; Board approved 90-day extension.
- approved5–0 · unanimousapprove 90-day extension of Site Plan and Subdivision Approval
View meeting recapDocuments8
- 20220831 Rendering- Brick Front- Angle (opens in a new tab)
1 page · 141 KB
Scanned document — no text preview
- 20220831 Rendering- Brick Front (opens in a new tab)
1 page · 132 KB
- Beacon-221006-Brick-3 (opens in a new tab)
Original could not be retrieved
- Street - Planning Board Extension Request (opens in a new tab)
11 pages · 588 KB
- May 12, 2026· New applicationDiscussedAmended Site Plan Approval
Review of Amended Site Plan Approval for 364 Main Street. Planner recused. Applicant's architect discussed architectural changes and field changes; constructed building has less square footage than approved. Board concerned about differences between approved and built design and impact on Main Street facade. Motion to circulate for lead agency approved.
- approvedunanimouscirculate for lead agency
View meeting recapDocuments1
- Beacon Views PB 5.12.26 ext request (opens in a new tab)
1 page · 47 KB
Scanned document — no text preview
- June 9, 2026· Continued reviewDiscussedAmended Site Plan Approval
Natalie Quinn recused herself. Taylor Palmer of Cuddy and Feder explained the applicant is seeking amended site plan approval for completed project changes that deviated from the approved plan. The board expressed frustration and demanded a comprehensive list of all deviations. Jason Anderson of ADG Architects discussed submission materials.
View meeting recapDocuments1
- 536 Main PB 6.9.26 Extension Request (opens in a new tab)
22 pages · 920 KB
This document is a cover letter dated May 26, 2026, requesting a one-year extension of Site Plan Approval for a three-story commercial building project at 536 Main Street in Beacon, New York, originally approved on June 13, 2023, with prior extensions granted in June 2024 and June 2025. The applicant (HRSM, LLC) states it continues to work toward satisfying approval conditions, including securing construction access agreements and obtaining the Chairman's endorsement of final site plans, and asserts that no material changes to the project or circumstances justify the extension request. The letter includes exhibits showing the original approval resolution and minutes from the June 2024 and June 2025 Planning Board meetings that granted previous extensions.
How it's moved
- Discussed3×
More at this address
Other applications on record for the same property.